Black Mountain Data Center (Southeast Fort Worth)

Southeast Fort Worth (near Forest Hill), Tarrant County

Black Mountain's flagship campus in southeast Fort Worth, reported at roughly $10 billion. The Fort Worth City Council voted 7–4 on August 25, 2026 to approve zoning changes and a revised 187-acre site plan — substantially smaller than the original proposal, cutting the project from 18 buildings and about 3 million square feet to four buildings totaling just over a million square feet. The revision increased the minimum distance between the facility and homes to 300 feet (from 150) and raised the maximum building height to 70 feet. Five council members had signed a letter in July 2026 calling for a moratorium on data center development. Tracked here because it is the same developer behind the proposed Parker County site.

Key facts

Location
Southeast Fort Worth (near Forest Hill), Tarrant County
Developer
Black Mountain (CEO Rhett Bennett)
Site size
187 acres
Water
Not confirmed.

About this location: Approximate location only — south of Lon Stephenson Road, east of Forest Hill Drive, west of Anglin Drive in southeast Fort Worth, roughly 30 miles east of Parker County. This project is NOT in or adjacent to Parker County; it is tracked here because it is the same developer as the proposed Parker County site.

Status timeline

  1. Statewide permit freeze takes effect

    Governor Abbott directed TCEQ to issue no permits sought by data center projects pending the ERCOT audit. Local zoning approval does not exempt a project from the state freeze.

  2. Council approves revised site plan, 7–4

    Council approved zoning changes and an amended 187-acre site plan: four buildings totaling just over a million square feet (down from 18 buildings and about 3 million square feet), a 300-foot minimum setback from homes, and a 70-foot maximum building height.

  3. Council members call for a moratorium

    Five members of the Fort Worth City Council signed a letter calling for a moratorium on data center developments, citing environmental impacts and strain on the power grid. (Month confirmed; exact day not confirmed.)

  4. Project stalls over resources and land use

    Fort Worth leaders raised concerns about resource use and land usage, slowing the $10 billion proposal.

  5. Initial rezoning approved

    Fort Worth City Council approved rezoning of roughly 160 acres at Forest Hill Drive and Lon Stephenson Road from agricultural to light industrial and Planned Development Specific Use. (Month confirmed; exact day not confirmed.)

In the news

Sources

Community-maintained tracker. Details — especially map locations and dates — are approximate and drawn from public reporting and government notices. Verify with the primary sources before acting. Last updated 2026-10-21. Spot something wrong?